A Cost-Loaded Schedule assigns budget values to activities so that progressing the programme automatically generates a time-phased cash-flow forecast and supports earned-value measurement. It links time and money in one model. On data-center projects a cost-loaded P6 schedule underpins the performance-measurement baseline, letting owners and contractors track planned versus earned versus actual cost across the build.
Category: Planning, Scheduling & Project Controls · Subcategory: Primavera P6 & Scheduling Structure · Part of the AIDC Technical Terminology reference.